Summary

This article explains how to plan crew on sick and their replacement in the Rotation Module.

Category

Knowledge Base Article

Keywords

Rotation Planning, Sick Leave


This article explains how to plan crew outlines the process for scheduling crew members on sick leave and organizing their replacement in replacements within the Rotation Module.

Table of Contents
minLevel1
maxLevel2
excludeContents
printablefalse

Step-by-step guide

  1. Add Enter the port details for the day when the sick crew member signs off and their replacement comesarrives.

    image-20240112-111100.png

  2. Select Choose the shift with of the crew member going on sick leave and change adjust its end date. Use For the subsequent days, apply the Create Gap/Overlap for the remaining days. Then function. Afterward, select the correct appropriate Sick activity to be added for fill the gap.

    image-20240112-111140.png
  3. Create Generate an additional extra shift for to cover the days when a replacement person comesindividual arrives.

    image-20240112-111148.png

  4. Assign the replacement person to the newly created shift.