APM POB and PPP Deviance
Module | Report Generator, Rotation Planning |
---|---|
Type | Regular Report |
Latest Version | 1.6.0 |
Summary | The report shows how much crew is scheduled for a relation Vessel Project / Rank. It is compared with the crew scheduled onboard & shows deviation. Info is shown split per vessel, project, rank category |
Description
POB - Personnel on board
PPP - Project personnel planning How to add Projects and Vessel Projects
The report shows how much crew is scheduled for a relation Vessel Project / Rank. It is compared with the crew scheduled onboard & shows deviation. Info is shown split per vessel, project, rank category
Dialog
Date - used to locate onboard number & Vessel Project crossing the date
Project:
Projects - the report uses Projects from Project Definition to compare the dates with the selected date.
Vessel Projects - the report compares Vessel Project dates with the selected date, so that only the projects linked to the selected vessel(s) are checked.
Vessels - to define vessel(s) of your interest
Activities - sea-service activities list to limit those that are counted as 'Onboard' for a given Vessel Project
Sample
Detail
Only the last non-planned activity before the dialog date is passed, so its off-signing crew change has not been confirmed.
Only ranks that are either onboard or set as required (or both) are included
Attachment